Skip to main content
Loading…
This section is included in your selections.

(a) Project Review. When the owner completes all required system upgrades and so advises WSSC, the Development Services Division will perform a final validation/inspection. Published results will be distributed as with pre-acceptance inspection results.

(b) As-Built Plan Requirements. After systems rehabilitation identified via the system evaluation have been certified, the owner must furnish the WSSC with a reproducible copy of the original drawings of the system, profiles, as-built plans or an acceptable plan of the system(s). The owner must submit the original or mylar of equal quality suitable for uploading. In addition to original drawings, the plan submittal shall include three complete sets of blue line prints. If the drawings were produced by a computer aided design (CAD) system, an AUTOCAD readable file shall also be submitted. The prepared drawings shall be consistent with WSSC plan design standards and shall conform to the following:

(1) Complete plans and profiles.

(2) Two-dimensional ties to all manholes, valves, water and sewer services, curb cocks, fire hydrants, etc. Ties must be to permanent physical objects, e.g., house or building corners, fire hydrants, manhole covers, utility poles identified by company and number, etc.

(3) As-built drawings shall be certified as reflecting true as-built conditions by a registered professional engineer licensed to practice in the State of Maryland.

(4) Consistent with WSSC design standards, as-built drawings shall be prepared on a scale of one inch to 30 feet for all town house and cluster development designs and one inch to 50 feet for all other development configurations.

(5) Locations of adjacent utilities and other features within the construction strip. (Amended during 2019 codification; PD 98-01 § IX)